About Us
Academic
Alumni
Calendar
Contact Us
Daily Announcements
ESL Information
Faculty
Forms
From the Principal
From the Assistant Principal
Graduation Project
Guidance Corner
Handbook
LCTI
Library
Lunch Menu
Resources
SADD
Sports
Physicals Paperwork
Staff
Student Activities
STSD

The Completed Building

Picture Credits: 1963 High School Dedication Book


All of the pictures are thumbnails.
Click on the picture to see a larger version.
Gymnasium Entrance
Auditorium Entrance
Office
Health Suite
Language Laboratory
Library
Audio Visual Room
Typing Room
Wood Working Shop
Metal Working Shop
Entrance to Homemaking Suite
Sewing Room
Food Preparation
Cafeteria


SCHOOL STATISTICS

Credits: 1963 High School Dedication Book

Site 26.65 acres
Size of building 90,800 square feet
1,267,858 cubic feet
Rated Capacity 858 pupils
Seating Capacity
Auditorium 530
Gymnasium 650
Cafeteria 290
Library 56
Play field 5.9 acres
Parking Area 280 cars
Annual Rental $130,000.00
Cost per square foot $19.63
Cost per cubic foot $1.41
Cost per pupil $2,308.85

Cost Data
General Construction $1,131,902.75
Heating and Ventilating $217,000.00
Electrical $179,370.00
Plumbing $118,824.50
Test Boring $13,600.00
Architects Fees $98,825.84
Movable Furniture and Equipment $131,060.00
Financing, Legal and Printing Cost $18,300.00
Project Supervision $8,000.00
Cost of Site $44,880.00
Miscellaneous Cost and Contingency $40,786.91
Total Cost (amount of Bond Issue) $2,000,000.00
Actual Cost $2,002,550.00
($2,550.00 to be paid by local funds for air conditioning)