The Completed Building
Picture Credits: 1963 High School Dedication Book
All of the pictures are thumbnails.
Click on the picture to see a larger version.
Gymnasium Entrance
| Auditorium Entrance
|
Office
| Health Suite
|
Language Laboratory
| Library
|
Audio Visual Room
| Typing Room
|
Wood Working Shop
| Metal Working Shop
|
Entrance to Homemaking Suite
| Sewing Room
|
Food Preparation
| Cafeteria
|
SCHOOL STATISTICS
Credits: 1963 High School Dedication Book
| Site
|
| 26.65 acres
|
| Size of building
|
| 90,800 square feet
|
|
|
| 1,267,858 cubic feet
|
| Rated Capacity
|
| 858 pupils
|
| Seating Capacity
|
|
|
|
|
| Auditorium
| 530
|
|
| Gymnasium
| 650
|
|
| Cafeteria
| 290
|
|
| Library
| 56
|
| Play field
|
| 5.9 acres
|
| Parking Area
|
| 280 cars
|
| Annual Rental
|
| $130,000.00
|
| Cost per square foot
|
| $19.63
|
| Cost per cubic foot
|
| $1.41
|
| Cost per pupil
|
| $2,308.85
|
Cost Data
| General Construction
|
| $1,131,902.75
|
| Heating and Ventilating
|
| $217,000.00
|
| Electrical
|
| $179,370.00
|
| Plumbing
|
| $118,824.50
|
| Test Boring
|
| $13,600.00
|
| Architects Fees
|
| $98,825.84
|
| Movable Furniture and Equipment
|
| $131,060.00
|
| Financing, Legal and Printing Cost
|
| $18,300.00
|
| Project Supervision
|
| $8,000.00
|
| Cost of Site
|
| $44,880.00
|
| Miscellaneous Cost and Contingency
|
| $40,786.91
|
| Total Cost (amount of Bond Issue)
|
| $2,000,000.00
|
| Actual Cost
|
| $2,002,550.00
|
| ($2,550.00 to be paid by local funds for air conditioning)
|
|






|
|